Modeling the problem of sequencing projects in the contractor’s portfolio of orders

Authors

DOI:

https://doi.org/10.24425/ace.2022.141887

Abstract

It is a usual practice for a contractor to deliver several projects at a time. Typically, the projects involve similar types of works and share the same pool of resources (i.e. construction crews). For this reason, the company’s portfolio of orders considered for a particular planning horizon can be modeled as a project with repeatable processes to be performed in heterogeneous units located in a number of construction sites. Its scheduling requires determining the best sequence of the resources’ moving from unit to unit while minding the due dates related with particular orders as well as resource continuity constraints. The authors present a model of this scheduling problem in the form of a mixed-integer linear program. The aim is to schedule a portfolio of projects in a way that minimizes the total of the resource idle time-related costs, the indirect costs, and the delay penalties. The model can be solved by means of a general-purpose solver. The model is applied to schedule a portfolio of multifamily housing projects.

References

[1] R.F. Aziz, “Optimizing strategy for repetitive construction projects within multi-mode resources”, Alexandria Engineering Journal, 2013, vol. 52, no. 1, pp. 67-81, DOI: 10.1016/j.aej.2012.11.003.

[2] A. Altuwaim, K. El-Rayes, “Optimizing the scheduling of repetitive construction to minimize interruption cost”, Journal of Construction Engineering and Management, 2018, vol. 144, no. 7, DOI: 10.1061/(ASCE)CO.1943-7862.0001510.

[3] I. Bakry, O. Moselhi, T. Zayed, “Optimized acceleration of repetitive construction projects”, Automation in Construction, 2014, vol. 1, pp. 145-151, DOI: 10.1016/j.autcon.2013.07.003.

[4] T.R. Browning, A.A. Yassine, “Resource-constrained multi-project scheduling: Priority rule performance revisited”, International Journal of Production Economics, 2010, vol. 126, no. 2, pp. 212-228, DOI: 10.1016/j.ijpe.2010.03.009.

[5] S.-L. Fan, K.-S. Sun, J.-R.Wang, “GA optimization model for repetitive projects with soft logic”, Automation in Construction, 2012, vol. 21, pp. 253-261, DOI: 10.1016/j.autcon.2011.06.009.

[6] S.-L. Fan, H.P. Tserng, M.-T. Wang, “Development of an object-oriented scheduling model for construction projects”, Automation in Construction, 2003, vol. 12, no. 3, pp. 283-302, DOI: 10.1016/S0926-5805(02)00092-4.

[7] S.-L. Fan, H.P. Tserng, “Object-oriented scheduling for repetitive projects with soft logics”, Journal of Construction Engineering and Management, 2006, vol. 132, no. 1, pp. 35-48, DOI: 10.1061/(ASCE)0733-9364(2006)132:1(35).

[8] J.D. García-Nieves, J.L. Ponz-Tienda, A. Ospina-Alvarado, M. Bonilla-Palacios, “Multipurpose linear programming optimization model for repetitive activities scheduling in construction projects”, Automation in Construction, 2019, vol. 105, DOI: 10.1016/j.autcon.2019.03.020.

[9] A. Gouda, O. Hosny, K. Nassar, “Optimal crew routing for linear repetitive projects using graph theory”, Automation in Construction, 2017, vol. 81, pp. 411-421, DOI: 10.1016/j.autcon.2017.03.007.

[10] T. Hegazy, E. Kamarah, “Efficient repetitive scheduling for high-rise construction”, Journal of Construction Engineering and Management, 2008, vol. 134, no. 4, DOI: 10.1061/(ASCE)0733-9364(2008)134:4(253).

[11] Z. Hejducki, J. Mrozowicz, “Stream methods of construction work organization: an introduction to the problem”, Engineering, Construction and Architectural Management, 2001, vol. 8, no. 2, pp. 80-89, DOI: 10.1108/eb021172.

[12] R. Huang, K.-S. Sun, “System development for non-unit based repetitive project scheduling”, Automation in Construction, 2005, vol. 14, no. 5, pp. 650-665, DOI: 10.1016/j.autcon.2005.02.003.

[13] R. Huang, K.-S. Sun, “A GA optimization model for workgroup-based repetitive scheduling (WoRSM)”, Advances in Engineering Software, 2009, vol. 40, no. 3, pp. 212-228, DOI: 10.1016/j.advengsoft.2008.01.010.

[14] P. Jaskowski, S. Biruk, “Scheduling of repetitive construction processes with concurrent work of similarly specialized crews”, Journal of Civil Engineering and Management, 2020, vol. 26, no. 6, pp. 579-589, DOI: 10.3846/jcem.2020.12914.

[15] X. Li, Q. Wang, C. Wu, “Heuristic for no-wait flow shops with makespan minimization”, International Journal of Production Research, 2008, vol. 46, no. 9, pp. 2519-2530, DOI: 10.1080/00207540701737997.

[16] L.D. Long, A. Ohsato, “A genetic algorithm-based method for scheduling repetitive construction projects”, Automation in Construction, 2009, vol. 18, no. 4, pp. 499-511, DOI: 10.1016/j.autcon.2008.11.005.

[17] S.-S. Liu, C.-J. Wang, “Optimizing linear project scheduling with multi-skilled crews”, Automation in Construction, 2012, vol. 24, pp. 16-23, DOI: 10.1016/j.autcon.2011.12.009.

[18] E. Mohamed, P. Jafari, A. Hammad, “Mixed qualitative-quantitative approach for bidding decisions in construction”, Engineering, Construction and Architectural Management, 2021, pp. 1-30, DOI: 10.1108/ECAM-12-2020-1060.

[19] M. Mucha, M. Sviridenko, “No-wait flowshop scheduling is as hard as Asymmetric Traveling Salesman Problem”, in Automata, Languages, and Programming, ICALP 2013; Lecture Notes in Computer Science, vol. 7965, F.V. Fomin, et. al., Eds. Berlin, Heidelberg: Springer, 2013, DOI: 10.1007/978-3-642-39206-1_65.

[20] J. Pekár, I. Brezina, J. Kultan, I. Ushakova, O. Dorokhov, “Computer tools for solving the traveling salesman problem”, Development Management, 2020, vol. 18, no. 1, pp. 25-39, DOI: 10.21511/dm.18(1).2020.03.

[21] D.C. Pinha, R.S. Ahluwalia, “Flexible resource management and its effect on project cost and duration”, Journal of Industrial Engineering International, 2019, vol. 15, pp. 119-133, DOI: 10.1007/s40092-018-0277-3.

[22] M. Podolski, “Scheduling of job resources in multiunit projects with the use of time/cost criteria”, Archives of Civil Engineering, 2016, vol. 62, no. 1, pp. 143-158, DOI: 10.1515/ace-2015-0057.

[23] J. Rieck, J. Zimmermann, T. Gather, “Mixed-integer linear programming for resource leveling problems”, European Journal of Operational Research, 2012, vol. 221, no. 1, pp. 27-37, DOI: 10.1016/j.ejor.2012.03.003.

[24] M. Rogalska, W. Bożejko, Z. Hejducki, “Time/cost optimization using hybrid evolutionary algorithm in construction project scheduling”, Automation in Construction, 2008, vol. 18, no. 1, pp. 24-31, DOI: 10.1016/j.autcon.2008.04.002.

[25] H. Samarghandi, M. Behroozi, “On the exact solution of the no-wait flow shop problem with due date constraints”, Computers & Operations Research, 2017, vol. 81, pp. 141-159, DOI: 10.1016/j.cor.2016.12.013.

[26] B.R. Sarker, P.J. Egbelu, W. Liaoa, J. Yu, “Planning and design models for construction industry: A critical survey”, Automation in Construction, 2012, vol. 22, pp. 123-134, DOI: 10.1016/j.autcon.2011.09.011.

[27] J.J. Shi, D.W. Halpin, “Enterprise resource planning for construction business management”, Journal of Construction Engineering and Management, 2003, vol. 129, no. 2, pp. 214-221, DOI: 10.1061/(ASCE)0733-9364(2003)129:2(214).

[28] B. Sroka, J. Rosłon, M. Podolski, W. Bożejko, A. Burduk, M. Wodecki, “Profit optimization for multi-mode repetitive construction project with cash flows using metaheuristics”, Archives of Civil and Mechanical Engineering, 2021, vol. 21, no. 67, DOI: 10.1007/s43452-021-00218-2.

[29] M. Tomczak, “Modeling of the harmonization method for executing a multi-unit construction project”, Open Engineering, 2019, vol. 9, no. 1, pp. 282-291, DOI: 10.1515/eng-2019-0036.

[30] M. Tomczak, P. Jaskowski, “Newapproach to improve general contractor crew’s work continuity in repetitive construction projects”, Journal of Construction Engineering and Management, 2020, vol. 146, no. 5, art. ID 4020043, DOI: 10.1061/(ASCE)CO.1943-7862.0001824.

[31] M. Vanhoucke, “Work Continuity Constraints in Project Scheduling”, Journal of Construction Engineering and Management, 2006, vol. 132, no. 1, pp. 14-25, DOI: 10.1061/(ASCE)0733-9364(2006)132:1(14).

[32] X. Zou, L. Zhang , Q. Zhang, “A biobjective optimization model for deadline satisfaction in Line-of-Balance scheduling with work interruptions consideration”, Mathematical Problems in Engineering, 2018, vol. 2018, art. ID 6534021, DOI: 10.1155/2018/6534021.

[33] X. Zou, G. Wu, Q. Zhang, “Work continuity constraints in repetitive project scheduling considering soft logic”, Engineering, Construction and Architectural Management, 2021, vol. 28, no. 6, pp. 1713-1738, DOI: 10.1108/ECAM-11-2019-0595.

Downloads

Published

2022-09-30

How to Cite

Jaśkowski, Piotr, et al. “Modeling the Problem of Sequencing Projects in the contractor’s Portfolio of Orders”. Archives of Civil Engineering, vol. 68, no. 3, Sept. 2022, pp. 307-22, doi:10.24425/ace.2022.141887.

Issue

Section

Articles

Similar Articles

<< < 25 26 27 28 29 30 31 32 33 34 > >> 

You may also start an advanced similarity search for this article.