Improving predictions of the Estimate at Completion using the classic Earned Value input

Authors

DOI:

https://doi.org/10.24425/ace.2024.151892

Abstract

The article investigates the author’s method of estimating the final cost of a construction investment. A list of proposed methods of calculating the value of the planned final cost of the EAC investment available in the world literature was used. The modification consisted in the first place in the verification and elimination of formulas that do not match the use in construction projects and the combination of formulas resulting in the same result. The study was aimed at enabling the right choice of the method of estimating the final cost of construction investments and determining the accuracy of this estimate. It should be emphasized that the analyzed investments were annexed many times during their implementation. On the basis of the obtained results of research carried out on real construction investments, it was found that 3 methods best predict the final cost of the investment. Finally, improvements were introduced, which were analyzed, the final effect of the article is a proposal of an original, universal formula, which in each of the analyzed construction investments, regardless of the trends, deviations from the cost at the time of the inspection, forecasts the most accurate result, consistent with reality. The conducted research gives the possibility of more effective financial management of a construction investment using the corrected EAC formula in EVM method.

References

[1] ANSI EIA – 748 Standard – Earned Value Management Systems.

[2] A. Webb, Using Earned Value – a project manager guide. Gower Publishing, Ltd., 2003.

[3] D. Przywara and A. Rak, “Monitoring of Time and Cost Variances of Schedule Using Simple Earned Value Method Indicators”, Applied Sciences, vol. 11, no. 4, art. no. 1357, 2021, doi: 10.3390/app11041357.

[4] J. Konior and M. Szóstak, “The S-Curve as a Tool for Planning and Controlling of Construction Process - Case Study”, Applied Sciences, vol. 10, no. 6, art. no. 2071, 2020, doi: 10.3390/app10062071.

[5] J. Konior and M. Szóstak, “Methodology of Planning the Course of the Cumulative Cost Curve in Construction Projects” Sustainability, vol. 12, no. 6, art. no. 2347, 2020, doi: 10.3390/su12062347.

[6] M. Trocki, et al., Modern project management. Warszawa: PWE, 2012.

[7] A. Webb, “Integrated cost and schedule control - a survey of UK experience”, The Engineering Journal, vol. 5, no. 3, 1995.

[8] T. Wilkens, Earned Value, Clear and Simple – Currently with Primavera System.1999.

[9] K. Heinze, Cost Management of Capital Projects. New York: Marcel Dekker, 1996.

[10] F. Anbari, Earned Value Project Management Method And Extensions. 2003.

[11] Department of Energy, USA, “Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting”, 2003.

[12] K. Athey, “EVM – Current Solution and Roadmap to Adoption”, 2007.

[13] G. A Barazza, “Probabilistic Estimation and Allocation of Project Time Contingence”, Journal of Construction Engineering and Management, vol. 137, no. 4, pp. 259-265, 2011, doi: 10.1061/(ASCE)CO.1943-7862.0000280.

[14] B. Flyvbjerg, M. S. Holm, and S. Buhl, “Underestimating Costs in Public Works”, American Planning Association Journal, vol. 68, no. 3, pp. 279-295, 2002.

[15] A. Mubarak Saleh, Construction Project Scheduling and Control. John Wiley & Sons, 2015.

[16] N. Kongchasing and G. Sua-Iam, “The major causes of construction delays identified using the Delphi technique: perspectives of contractors and consultants in Thailand”, International Journal of Civil Engineering, vol. 19, pp. 319-338, 2021, doi: 10.1007/s40999-020-00575-8.

[17] K. Park, H.W. Lee, K. Choi, et al., “Project Risk Factors Facing Construction Management Firms”, International Journal of Civil Engineering, vol. 17, pp. 305-321, 2019, doi: 10.1007/s40999-017-0262-z.

[18] M. Bilal, et al., “Investigating profitability performance of construction projects using big data: A project analytics approach”, Journal of Building Engineering, vol. 26, 2019, doi: 10.1016/j.jobe.2019.100850.

[19] T. Chen, et al., “How do project management competencies change within the project management career model in large Chinese construction companies?”, International Journal of Project Management, vol. 37, no. 3, pp. 485-500, 2019, doi: 10.1016/j.ijproman.2018.12.002.

[20] U. Dwivedi, “Earned Value Management Explained”, Project Smart, 2019. [Online]. Available: https://www.projectsmart.co.uk/earned-value-management-explained.php.

[21] L. Lin, et al., “Choosing suitable project control modes to improve the knowledge integration under different uncertainties”, International Journal of Project Management, vol. 37, no. 7, pp. 896-911, 2019, doi: 10.1016/j.ijproman.2019.07.002.

[22] L. Song, Earned Value Management: A Global Cross-Industry Perspective on Current EVM Practice. PMI, 2010.

[23] M. Danso-Amoako, et al., “Building information modeling for facilities management: A literature review and future research directions”, Journal of Building Engineering, vol. 24, 2019, doi: 10.1016/j.jobe.2019.100755.

[24] N. Moradi, et al., “An earned value model with risk analysis for project management under uncertain conditions”, Journal of Intelligent & Fuzzy Systems, vol. 32, pp. 97-113, 2017, doi: 10.3233/JIFS-151139.

[25] A. Starczyk-Kołbyk and L. Kruszka, “The influence of construction works disturbances on the EVM analysis outcomes - case study”, Archives of Civil Engineering, vol. 66, no. 1, pp. 161-177, 2020, doi: 10.24425/ace.2020.131781.

[26] J. Batselier and M. Vanhoucke, “Evaluation of deterministic state-of-the-art forecasting approaches for project duration based on earned value management”, International Journal of Project Management, vol. 33, no. 7, pp. 1588-1596, 2015, doi: 10.1016/j.ijproman.2015.04.003.

[27] P. Efe and O. Demirors, “A change management model and its application in software development projects”, Computer Standards & Interfaces, vol. 66, 2019, doi: 10.1016/j.csi.2019.04.012.

[28] A. M. Alsugair, et al., “Artificial Neural Network Model to Predict Final Construction Contract Duration”, Applied Sciences, vol. 13, no. 14, art. no. 8078, 2023, doi: 10.3390/app13148078.

[29] C. Daegu, et al., “Development of Cost and Schedule Data Integration Algorithm Based on Big Data Technology”, Applied Sciences, vol. 10, no. 24, art. no. 8917, 2020, doi: 10.3390/app10248917.

[30] T. Kasprowicz and A. Starczyk-Kołbyk, “Randomized Earned Value Method for the rolling assessment of construction projects advancement”, Archives of Civil Engineering, vol. 68, no. 2, pp. 501-520, 2022, doi: 10.24425/ACE.2022.140655.

[31] T. Kasprowicz, A. Starczyk-Kołbyk, and R. R. Wójcik, “The randomized method of estimating the net present value of construction projects efficiency”, International Journal of Construction Management, vol. 23, no. 12, pp. 2126-2133, 2023, doi: 10.1080/15623599.2022.2045426.

[32] T. Kasprowicz, A. Starczyk-Kołbyk, and R. R. Wójcik, “Randomized Estimation of the Net Present Value of a Residential Housing Development”, Applied Sciences, vol. 12, no. 1, 2022, doi: 10.3390/app12010124.

Downloads

Published

2024-12-30

How to Cite

Starczyk-Kołbyk, Anna. “Improving Predictions of the Estimate at Completion Using the Classic Earned Value Input”. Archives of Civil Engineering, vol. 70, no. 4, Dec. 2024, pp. 271-89, doi:10.24425/ace.2024.151892.

Issue

Section

Articles

Similar Articles

<< < 41 42 43 44 45 46 47 48 49 50 > >> 

You may also start an advanced similarity search for this article.