Reactive scheduling of repetitive construction projects by allocating additional resources

Authors

DOI:

https://doi.org/10.24425/ace.2025.156188

Abstract

Repetitive construction projects involve the sequential execution of the same type of construction process at different locations (units). Work crews responsible for a particular type of process complete their work in one unit and then move on to the next. In practice, it is not possible to divide the built facility into identical units. In such a case, reducing the execution time of the project leads to interruptions in the workflow of the crews. Better results can be achieved by changing the order in which the units are processed by the crews. The use of the flow-shop system, well known in production scheduling, makes it possible to reduce the execution time of this type of projects, but makes the schedules vulnerable to random disturbances: the resulting delays can propagate throughout the schedule and generate idle time for crews completing their processes on time. Therefore, rescheduling may become inevitable to meet the deadlines. This paper presents a linear programming mathematical model for reactive scheduling that takes into account the possibility of allocating additional crews and allows for the possibility of changing the sequence of units. It makes it possible to meet the target date for completion of the project and to reduce the downtime of the working crews. The proposed approach to respond to schedule disruptions is illustrated by an example. Potential tools for solving the model were also pointed out, which can form the basis for creating a decision support system in the execution phase of repetitive projects.

References

[1] V.S. Nguyen, H.-H. Nguyen, D.A. Nguyen, and D.T. Hai, “Delay factors in the construction of irrigation and hydropower projects in Vietnam”, Archives of Civil Engineering, vol. 69, no. 1, pp. 5-20, 2023, doi: 10.24425/ace.2023.144156.

[2] W. Herroelen and R. Leus, “Project scheduling under uncertainty: Survey and research potentials”, European Journal of Operational Research, vol. 165, no. 2, pp. 289-306, 2005, doi: 10.1016/j.ejor.2004.04.002.

[3] F. Deblaere, E. Demeulemeester, and W. Herroelen, “Reactive scheduling in the multi-mode RCPSP”, Computers & Operations Research, vol. 38, no. 1, pp. 63-74, 2011, doi: 10.1016/j.cor.2010.01.001.

[4] P. Jaśkowski, S. Biruk, This work was funded under the grant "Subvention for Science" (MEiN), project no. FN-06, FN-10, FD-20/IL-4/005, FD-20/IL-4/026.d M. Krzemiński, “Planning repetitive construction processes to improve robustness of schedules in risk environment”, Archives of Civil Engineering, vol. 66, no. 3, pp. 643-657, 2020, doi: 10.24425/ace.2020.134418.

[5] M. Tomczak and P. Jaśkowski, “Scheduling repetitive construction projects: structured literature review”, Journal of Civil Engineering and Management, vol. 28, no. 6, pp. 422-442, 2022, doi: 10.3846/jcem.2022.16943.

[6] P. Jaśkowski and S. Biruk, “The method for improving stability of construction project schedules through buffer”, Technological and Economic Development of Economy, vol. 17, no. 3, pp. 429-444, 2011, doi: 10.3846/20294913.2011.580587.

[7] This work was funded under the grant "Subvention for Science" (MEiN), project no. FN-06, FN-10, FD-20/IL-4/005, FD-20/IL-4/026. P. Jaśkowski, S. Biruk, and M. Krzeminski, “Proactive-reactive repetitive project scheduling method – the concept of risk consideration at the project planning and execution stage”, Archives of Civil Engineering, vol. 69, no. 4, pp. 89-104, 2023, doi: 10.24425/ace.2023.147649.

[8] I. Bakry, O. Moselhi, and T. Zayed, “Optimized acceleration of repetitive construction projects ”, Automation in Construction”, vol. 39, pp. 145-151, 2014, doi: 10.1016/j.autcon.2013.07.003.

[9] T. Hegazy and E. Kamarah, “Schedule optimization for scattered repetitive projects”, Automation in Construction”, vol. 133, art. no. 104042, 2022, doi: 10.1016/j.autcon.2021.104042.

[10] Z.M. Al Sarraj, “Formal development of Line-of-Balance technique”, Journal of Construction Engineering and Management, vol. 116, no. 4, pp. 689-704, 1990, doi: 10.1061/(ASCE)0733-9364(1990)116:4(689).

[11] This work was funded under the grant "Subvention for Science" (MEiN), project no. FN-06, FN-10, FD-20/IL-4/005, FD-20/IL-4/026. T. Hegazy, K. Mostafa, and S. Ojulari, “Tetris-inspired approach for generating tightly-packed repetitive schedules”, Automation in Construction, vol. 124, art. no. 103601, 2021, doi: 10.1016/j.autcon.2021.103601.

[12] L. Zhou and Y. Li, “Optimization study of Construction repetitive project scheduling based on big data background”, Archives des Sciences, vol. 74, no. 2, pp. 91-99, 2024, doi: 10.62227/as/74213.

[13] M. Tomczak and P. Jaśkowski, “Crashing construction project schedules by relocating resources”, IEEE Access, vol. 8, pp. 224522-224531, 2020, doi: 10.1109/ACCESS.2020.3044645.

[14] W.E. Whiteman and H.G. Irwig, “Disturbance scheduling technique for managing renovation work”, Journal of Construction Engineering and Management, vol. 114, no. 2, pp. 191-213, 1988, doi: 10.1061/(ASCE)0733-9364(1988)114:2(191).

[15] W.Y. Thabet and Y.J. Beliveau, "HVLS: Horizontal and Vertical Logic Scheduling for Multistory Projects", Journal of Construction Engineering and Management, vol. 120, no. 4, pp. 875-892, 1994, doi: 10.1061/(ASCE)0733-9364(1994)120:4(875).

[16] A.C. Russell and W.F. Caselton, “Extensions to Linear Scheduling Optimization”, Journal of Construction Engineering and Management, vol. 114, no. 1, pp. 36-52, 1988, doi: 10.1061/(ASCE)0733-9364(1988)114:1(36).

[17] R.B. Harris and P.G. Ioannou, “Scheduling Projects with Repeating Activities”, Journal of Construction Engineering and Management, vol. 124, no. 4, pp. 269-278, 1998, doi: 10.1061/(ASCE)0733-9364(1998)124:4(269).

[18] K. El-Rayes, “Optimum planning of highway construction under A + B bidding method”, Journal of Construction Engineering and Management, vol. 127, no. 4, pp. 261-269, 2001, doi: 10.1061/(ASCE)0733-9364(2001)127:4(261).

[19] K. Hyari and K. El-Rayes, “Optimal planning and scheduling for repetitive construction projects”, Journal of Management in Engineering, vol. 22, no. 1, pp. 11-19, 2006, doi: 10.1061/(ASCE)0742-597X(2006)22:1(11).

[20] P.G. Ipsilandis, “Multiobjective Optimization in Linear Repetitive Project Scheduling”, Operational Research. An International Journal, vol. 6, no. 3, pp. 255-269, 2006, doi: 10.1007/BF02941255.

[21] T. Hegazy and E. Kamarah, “Efficient repetitive scheduling for high-rise construction”, Journal of Construction Engineering and Management, vol. 134, no. 4, pp. 253-264, 2008, doi: 10.1061/(ASCE)0733-9364(2008)134:4(253).

[22] F.A. Agrama, “Multi-objective genetic optimization for scheduling a multi-storey building”, Automation in Construction, vol. 44, pp. 119-128, 2014, doi: 10.1016/j.autcon.2014.04.005.

[23] T. Salama and O. Moselhi, „Multi-objective optimization for repetitive scheduling under uncertainty”, Engineering, Construction and Architectural Management, vol. 26, no. 7, pp. 1294-1320, 2019, doi: 10.1108/ECAM-05-2018-0217.

[24] M.A. Roghabadi and O. Moselhi, “Optimized crew selection for scheduling of repetitive projects”, Engineering Construction and Architectural Management, vol. 28, no. 6, pp. 1517-1540, 2021, doi: 10.1108/ECAM-10-2019-0590.

[25] G. Dai, M. Liao, and R. Zhang, “Resource levelling in repetitive construction projects with interruptions: an integrated approach”, Journal of Civil Engineering and Management, vol. 29, no. 2, pp. 93-106, 2023, doi: 10.3846/jcem.2023.17568.

[26] M. Tomczak and P. Jaśkowski, “Customized particle swarm optimization for harmonizing multi-section construction projects”, Automation in Construction, vol. 162, art. no. 105359, 2024, doi: 10.1016/j.autcon.2024.105359.

[27] Z. Hejducki and Z.J. Mrozowicz, “Stream methods of construction work organization: an introduction to the problem”, Engineering, Construction and Architectural Management, vol. 8, no. 2, pp. 80-89, 2001, doi: 10.1108/eb021172.

[28] E. Radziszewska-Zielina and B. Sroka, “Priority scheduling in the planning of multiple-structure construction projects”, Archives of Civil Engineering, vol. 63, no. 4, pp. 21-33, 2017, doi: 101515/ace-2017-0038.

[29] E. Radziszewska-Zielina and B. Sroka, “Planning repetitive construction projects considering technological constraints”, Open Engineering, vol. 8, no. 1, pp. 500-505, 2018, doi: 10.1515/eng-2018-0058.

[30] M. Podolski, ”Management of resources in multiunit construction projects with the use of a tabu search algorithm”, Journal of Civil Engineering and Management, vol. 23, no. 2, pp. 263-272, 2017, doi: 10.3846/13923730.2015.1073616.

[31] Y. Huang, X. Zou, and L. Zhang, “Genetic algorithm-based method for the deadline problem in repetitive construction projects considering soft logic”, Journal of Management in Engineering, vol. 32, no. 4, art. no. 04016002, 2016, doi: 10.1061/(ASCE)ME.1943-5479.0000426.

[32] P. Jaskowski and S. Biruk, “Scheduling of repetitive construction processes with concurrent work of similarly specialized crews”, Journal of Civil Engineering and Management, vol. 26, no. 6, pp. 579-589, 2020, doi: 10.3846/jcem.2020.12914.

[33] P. Jaśkowski, S. Biruk, and M. Krzemiński, „Modeling the problem of sequencing projects in the contractor’s portfolio of orders”, Archives of Civil Engineering, vol. 68, no. 3, pp. 307-322, 2022, doi: 10.24425/ace.2022.141887.

[34] S. Tamimi and J. Diekmann, “Soft logic in network analysis”, Journal of Computing in Civil Engineering, vol. 2, no. 3, pp. 289-300, 1988, doi: 10.1061/(ASCE)0887-3801(1988)2:3(289).

[35] S.-L. Fan, K.-S. Sun, and Y.-R.Wang, “GA optimization model for repetitive projects with soft logic”, Automation in Construction, vol. 21, pp. 253-261, 2012, doi: 10.1016/j.autcon.2011.06.009.

Downloads

Published

2025-12-30

How to Cite

Jaśkowski, Piotr, et al. “Reactive Scheduling of Repetitive Construction Projects by Allocating Additional Resources”. Archives of Civil Engineering, vol. 71, no. 4, Dec. 2025, pp. 559-72, doi:10.24425/ace.2025.156188.

Issue

Section

Articles

Similar Articles

<< < 41 42 43 44 45 46 47 48 > >> 

You may also start an advanced similarity search for this article.